Q. What are Fabcon's lead times?A. Lead times (as defined by Fabcon) include the production of shop drawings as well as production time and delivery to the job site. Lead times can vary depending on workload, but the typical processes of drawing and production take eight weeks. While projects can be processed in a shorter period of time, eight weeks allows sufficient time for drawing review, etc. Lead times can also extend beyond eight weeks depending on the backlog of work. |